    Default Workflow Tasks and Due Dates

    I can not figure out how to setup a workflow that says:


    "If todays date > due date, send email to whoever"

    I have cases that when built a workflow creates tasks such as

    1. notify customer
    2. confirm order

    I set the due date to 2 days after trigger date. this all works fine

    now i want to keep a constant check to see if any of these tasks are overdue.


    Thanks

    Bart

  2. #2
    LPinner is offline Member
    Join Date
    Jul 2010
    Location
    Illinois, USA
    Posts
    7

    Default Re: Workflow Tasks and Due Dates

    Has anyone found an answer to this question? I have the same question.

    Thanks,
    Lundie

  3. #3
    chrislynch8's Avatar
    chrislynch8 is offline Sugar Community Member
    Join Date
    Oct 2007
    Location
    Cork, Ireland
    Posts
    747

    Default Re: Workflow Tasks and Due Dates

    Hi,

    What you can do is.

    1: When creating the task with the workflow based on a Case, set the task a Status (Whichever You Like)
    2: Create a time based workflow on the task that will trigger is the Status has not changed after 2 days for example.

    Rgds
    Chris
    Linkedin Profile:Chris Lynch

    FDC IT Solutions
    FDC House
    Wellington Road
    Cork
    Ireland

  4. #4
    LPinner is offline Member
    Join Date
    Jul 2010
    Location
    Illinois, USA
    Posts
    7

    Default Re: Workflow Tasks and Due Dates

    Thanks for the quick response, but unfortunately that's not what I need.

    We have activity tasks that are created with a due date (tied to a variety of records - account, case, contact, etc.).

    When that due date passes, I want an email sent to the person assigned, reminding them that the task is now past due. That's all.

    Regards,
    Lundie

  5. #5
    chrislynch8's Avatar
    chrislynch8 is offline Sugar Community Member
    Join Date
    Oct 2007
    Location
    Cork, Ireland
    Posts
    747

    Default Re: Workflow Tasks and Due Dates

    OK sorry,

    Just create a Time based Workflow and set the trigger to due_date was more then a specified time ago, you choose them from a dropdown i.e. 1 day, 1 week, etc... This is built into the Workflows already.

    Rgds
    Chris
    Linkedin Profile:Chris Lynch

    FDC IT Solutions
    FDC House
    Wellington Road
    Cork
    Ireland

  6. #6
    LPinner is offline Member
    Join Date
    Jul 2010
    Location
    Illinois, USA
    Posts
    7

    Thumbs up Re: Workflow Tasks and Due Dates

    Thanks for the redirection!

    The terminology in the options is not very clear. In case other searchers come across this, this is what I did.

    • Create a workflow with "Execution Occurs: After Time Elapses", and "Target Module: Tasks", and "Applies To: New and Updated Records"
    • Add a condition with "When a field in the target module changes to or from a specified value" where "field: Due Date", then "Specify new ' Due Date: ' value:" "was more than (or is less than)" "X time ago (Or is X time from now)"


    Have a great day!

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 4
    Last Post: 2009-03-31, 12:09 PM
  2. Replies: 0
    Last Post: 2009-01-22, 05:58 PM
  3. Set due date for tasks in workflow possible?
    By karelgeenen in forum Help
    Replies: 1
    Last Post: 2008-08-04, 02:54 PM
  4. Tasks dates & times
    By Triffid in forum Help
    Replies: 2
    Last Post: 2007-10-07, 07:58 PM
  5. Assign tasks using workflow
    By John Burton in forum General Discussion
    Replies: 1
    Last Post: 2007-07-29, 05:50 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •